ASAP Phases

AcceleratedSAP Phases

Phase 1 – Project Preparation

Phase 2 – Business Blueprint

Phase 3 – Realization

Phase 4 – Final Preparation

Phase 5 – Go Live and Support



The ASAP Roadmap was developed by SAP to help customers implement SAP software in a quick, cost-effective manner. Utilizing this approach:
·         minimizes the length of implementation,
·         maximizes the utilization of TeamSAP and customer resources,
·         results in a “Repetitive Model” that can be used with other implementations of SAP modules or systems, and
·         provides a process-oriented approach to Product Training.



Project Preparation Key Activities and Deliverables

Key Activities
Deliverables
·         Finalize Project Team Organization

·         Project Team Structure Organization Chart
·         Finalize Project Team Training Plan

·         Project Team Training Schedule
·         Define Team Facilities Requirements

·         Project Team Seating Chart (including required equipment)
·         Develop Project Plans
·         Baseline Project Plans
·         Initial Activities Planned
·         Resource Plan
·         Develop Project Strategies and Scope






·         Review Existing Implementations
·         Draft:
o   Implementation Strategy
o   End-User Training Strategy
o   Development Strategies
o   Testing Strategy
o   Technical Strategies
o   Security and Controls Strategy
o   High-level Project Scope Document
·         List of Lessons Learned
·         Define Project Management Standards and Procedures
·         Project Management Standards and Procedures (Issue Mgt Plan, Status Report Format, Change Control Forms, Documentation standards, etc,)
·         Develop Benefits Realization Strategy
·         Benefits Realization Approach
·         Develop Project Risk Assessment
·         Risk Management Plan, Report and recommendations to mitigate project risks, and summary of Critical Success Factors
·         Define Post-Implementation Support
·         Post-Implementation Support Approach
·         Perform Technical Requirements Gathering
·         Complete Technical Questionnaires
·         Define Technical Infrastructure Needs
·         Procure Hardware
·         Size Initial Hardware
·         Approve Sizing Results
·         Order Initial Hardware and Software
·         Order Remote Network Connection
·         Define System Landscape Strategy
·         System Landscape Strategy
·         Define Project Methodologies, Tools and Project Governance Standards
·         Established Project Methodologies, Tools and Governance Standards
·         Define Quality Assurance Plan
·         Quality Assurance Plan
·         Develop Communication Strategy and Plan
·         Communication Plan/Strategy
·         Confirm Process, Organization and Technical Scope
·         Sign-off by Customer
·         Develop and perform Change Readiness Assessment
·         Change Readiness Assessment Results and Report
·         Produce and Deliver Program Management Status Reports
·         Completed Status Report
·         Updated Issues Log
·         Prepare for Project Kickoff
·         Kickoff Meeting




Business Blueprint Key Activities and Deliverables

Key Activities
Deliverables
·         Conduct Project Team Training

·         Execute Project Team Training Schedule
·         Define SAP Organizational Structure
·         Define Global Parameters
·         SAP R/3 Hierarchy Definitions
·         Prepare for Blueprint Workshops

·         Blueprint Workshop Schedule
·         List of Blueprint Workshop Participants
·         Blueprint Workshop Agendas
·         Conduct Blueprint Workshops
·         Business Blueprint Report
o   Business Process Flows
o   Policies and Procedures
o   Gaps Identified
·         Business Process Master List (BPML)
·         Finalize Project Scope
·         Finalized Scope Document Signed off by Customer
·         Finalize Development Scope
·         Development Scope: Reporting, Interfaces, Conversions, Enhancements
·         Finalize End-User Training Strategy
·         End-User Training Strategy Signed-Off by Customer
·         End User Training Requirements and Materials Standards document
·         Conform to DoD RICE Concept of Operations
·        
·         Perform Cycle Planning for Prototyping
·         Cycle Plan for Prototyping
·         Develop Knowledge Transfer Plan
·         Knowledge Transfer Plan signed off by Customer
·         Develop Communications and Key Stakeholder Management Plans
·         Communication and Key Stakeholder Management Plans
·         Define Business Organization Structure and Identify Impact Areas
·         Business Organization Impacts
·         Complete SAP Bolt-On Evaluation
·         Evaluation Results of SAP Bolt-Ons
·         Identify Process Ownership
·         Benefits and Process Owner Organization
·         Create Technical Design
·         Technical Design Document
·         Develop Non-functional Requirements
·         Non-functional Requirements Specifications Documentation
·         Develop Security Requirements
·         Security Requirements Specifications Documentation
·         Setup and Install Development Environment
·         Installed Development System
·         Risk Assessment Measurement
·         Revised Risk Assessment
·         Conduct Peer/Solution/Technical Reviews
·         Solution/Technical Review Findings Reports
·         Produce and Deliver Program Management Status Reports
·         Completed Status Report
·         Updated Issues Log
·         Business Blueprint Sign-off
·         Business Blueprint Documentation and Phase completion signed-off by Customer




Realization Key Activities and Deliverables

Key Activities
Deliverables
·         Define Master Data
·         Master Data Definitions
·         Baseline Configuration Completed
·         Baseline Configuration and Documentation
·         Conduct Unit Testing

·         Completed Unit Testing and Associated Scripts and Results
·         Final Configuration Completed
·         Configured SAP System and Related Documentation
·         Create Security Authorizations
·         Configured SAP User Profiles and Roles
·         Develop Custom Design Specifications (functional spec’s)
·         Functional Specifications
·         Develop Technical and Functional Specifications
·         Technical and Functional Specifications Documentation and Associated Approvals
·         Coding and Unit Test for Conversions, Reports, Interfaces and Enhancements
·         Completed Unit Testing for Development Objects
·         Object Code for Development Objects
·         Conversion Planning (Cutover) and Preparation
·         Initial Conversion (Cutover) Plan
·         Draft Legacy Retirement Plan
·         Develop New Procedures and Policies
·         New Procedures and Policies Documented/Approved
·         Finalize Implementation Strategy
·         Implementation Strategy, including Site Readiness Assessment and Change Process Improvement
·         Finalize End-User Training Strategy
·         Approved End-User Training Strategy
·         Establish Training Environment
·         Installed Training System
·         Train Power Users
·         Trained Power Users and Trainers
·         Plan SAP early watch Go-Live Quality Assurance / Check
·        
·         Plan and Execute System Test
·         System Test Plan
·         Volume and Stress Tested System
·         Execute Cycle Testing
·         Cycle Testing Complete
·         Develop Integration Test Plan(s)
·         Integration Test Plan
·         Execute Integration Test
·         Integration Test Complete
·         Design and Deliver Instructor Training Material (if applicable)
·         Instructor Training Material
·         Create End-User Training Programs and Training Materials
·         End-User Training Curriculum
·         End-User Training Materials
·         End-User Training Schedule
·         Facilities Reservations
·         Create Technical Design
·         Technical Design Document
·         Establish Data Archiving Plan
·         Data Archiving Plan
·         Setup and Install Quality Assurance (QA) Environment
·         Installed Quality Assurance System
·         Risk Assessment Measurement
·         Revised Risk Assessment
·         Deliver Knowledge Transfer Status
·        
·         Execute Communications Plan
·         Presentations
·         Newsletters
·         Conduct Peer/Solution/Technical Reviews
·         Solution/Technical Review Findings Reports
·         Produce and Deliver Program Management Status Reports
·         Completed Status Report
·         Updated Issues Log




Final Preparation Key Activities and Deliverables

Key Activities
Deliverables
·         Perform System Tests
·         Execute Stress, Volume, Disaster Recovery and Backup Tests
·         Technical Processes Tested
·         Assess Going-Live Check Recommendations
·         Implement Going-Live Check Recommendations
·         Finalize Cutover (Conversion) Plan
·         Cutover Workplan
·         Develop Contingency Plan

·         Contingency Plan
·         Refine and Execute Production Support Plan
·         Commence Initial Production Support Activities (which occur prior to go-live)
·         Execute Change Plan
·         Organization Change Plan
·         Production Readiness Review
·        
·         Obtain Cutover Approval
·         Execute Cutover/Conversion Plan
·         Refine and Execute Legacy Retirement Plan
·         Legacy Retirement Plan
·         Perform Training Program Evaluation
·         Training Program Evaluation
·         Deliver End-User Training
·         Trained End Users
·         Complete Process and Organizational Changes
·         Process and Organizational Changes Performed
·         Execute SAP Going-Live Check
·         Going Live Check Assessment
·         Develop Technical Operations Manual
·         Technical Operations Manual
·         Setup and Install Production Environment(s)
·         Installed Production System(s)
·         Configure and Execute System Administrator Functionality
·         Tuned SAP System
·         Establish Service Level Agreements
·         Service Level Agreements
·         Risk Assessment Measurement
·         Revised Risk Assessment
·         Conduct Peer/Solution/Technical Reviews
·         Solution/Technical Review Findings Reports
·         Produce and Deliver Program Management Status Reports
·         Completed Status Report
·         Updated Issues Log
·         Final Preparation Sign-off
·         Go-Live Approved





Go-Live and Support Key Activities and Deliverables

Key Activities
Deliverables
·         Provide Production Support (Help Desk)
·         Production Support (Help Desk) Established
·         Execute Daily Operation Support and Administration
·         Optimize System Tuning
·         Production-Ready Systems Environment
·         Validate Live Business Process Results
·         Business Process Results
·         Monitor Transactions, Interfaces and Procedures
·         System tuning and Procedural Updates
·         Execute Ongoing Security Administration
·         Security Administration
·         Provide Ongoing Training Support
·         Execute Ongoing Training Support
·         Develop Continuous Improvement Plan
·         Continuous Improvement Plan
·         Produce and Deliver Program Management Status Reports
·         Completed Status Report
·         Updated Issues Log
·         Post Implementation Review
·         Post Implementation Findings Reports